64th St Townhomes: Q3 2026 Construction Update, Completed and Move-In Ready

64th St Townhomes are four townhomes in two buildings in Ballard. Both buildings finished construction in September 2026, and the homes are move-in ready. This update looks back at how the project went from start to finish.
Progress at a glance
- Permit issuedComplete
- DemolitionComplete
- FoundationsApril 2026
- FramingJuly 2026
- Construction completeSeptember 2026
- Move-in readyNow
Status as of late September 2026, from the Q2 2026 report. Confirm the final inspection result before publishing.
How construction went
- Site and foundations (April 2026): under-slab insulation, rebar and utility work between the buildings, then slabs poured on both.
- Framing (April to July 2026): wall framing started on the 2013 building as the slabs cured. Upper floors rose on the 2017 building, and both roofs were sheathed.
- Roofing (May 2026): roofing was complete on both buildings by May 20.
- Envelope and rough-in (May and June 2026): mechanical, electrical and plumbing rough-in began in May. Windows were in and siding underway on both buildings by late June, and drywall started before the end of the quarter.
- Completion (September 2026): construction finished on the 2017 building (units 3 and 4) on September 15 and on the 2013 building (units 1 and 2) on September 22.
- Unit lot subdivision: recorded, so each home sits on its own lot.
What a buyer sees today
The homes are finished and move-in ready. For floor plans and current availability, see the community page.