Phinney Ridge Townhomes are eight townhomes in two buildings of four, in the neighborhood where Olsen Anderson began. As of October 2026, the north building is framed to the roof and framing has started on the south building.

Progress at a glance

  1. Permit issuedApril 2026
  2. DemolitionMay 2026
  3. Excavation and soilsJune 2026
  4. FoundationsSeptember 2026
  5. FramingNorth building framed; south building started
  6. Construction completeUpcoming

Status as of early October 2026. Dates for future milestones are not shown because they can change.

Where construction stands

How the site got here

What is next

Framing both buildings, and finishing the underground power work in the street.

Photos

Overhead view of the framing at Phinney Ridge Townhomes
Oct 2026. Framing, from above.
Aerial view of the framed Phinney Ridge Townhomes building among neighboring houses
Oct 2026. The framed north building and the south building site behind it, in the neighborhood.
Overhead view of floor framing on the north building at Phinney Ridge Townhomes
Oct 2026. Floor framing on the north building.