Phinney Ridge Townhomes: Q2 2026 Construction Update

Phinney Ridge Townhomes are eight townhomes in two buildings of four, in the neighborhood where Olsen Anderson began. As of October 2026, the north building is framed to the roof and framing has started on the south building.
Progress at a glance
- Permit issuedApril 2026
- DemolitionMay 2026
- Excavation and soilsJune 2026
- FoundationsSeptember 2026
- FramingNorth building framed; south building started
- Construction completeUpcoming
Status as of early October 2026. Dates for future milestones are not shown because they can change.
Where construction stands
- North building: framed to the top floor, with roof trusses set by crane in October.
- South building: slab ready, and framing has started.
- Foundations: complete in September 2026. Framing began on September 28.
How the site got here
- May: the two existing houses were demolished.
- May and June: excavation and soil removal, then a gravel base, footing trenches, and drainage piping ahead of the foundation.
- Design note: the site was designed around the cedar trees retained on the property.
What is next
Framing both buildings, and finishing the underground power work in the street.