Roen: Q2 2026 Construction Update

Roen is ten brick townhomes on the west edge of Queen Anne, with roof decks over the Sound. As of early October 2026, framing is complete on three of the four buildings and exterior finishes have started on the first buildings.
Progress at a glance
- Permit issuedComplete
- DemolitionComplete
- FoundationsComplete
- Framing3 of 4 buildings done
- Exterior finishesUnder way on first buildings
- Construction completeUpcoming
Status as of early October 2026, from the Q2 2026 report. Dates for future milestones are not shown because they can change.
Where construction stands
- Buildings 1 to 3: framing is complete. Exterior finishes are underway on the first buildings.
- Building 4: in framing.
- Foundations: complete across the site.
What changed this quarter
- Foundations finished across the site. Slabs were insulated and poured, and footings and foundation walls were formed for the remaining buildings.
- Framing started on the first building in April and had reached the upper floors by May.
- A crane on site supported the first building while later foundations went in.
What is next
Finishing framing on the last building, then the power and sidewalk work in the street.
Photos