The Henrie: Q2 2026 Construction Update
The Henrie is 21 townhomes in three buildings at the top of Capitol Hill. As of October 2026, Building A is finishing, and Buildings B and C are closed in.
Progress at a glance
- Permit issuedComplete
- DemolitionComplete
- FoundationsJune 2026
- FramingComplete
- Condominium recordedOctober 2026
- FinishingBuilding A finishing; B and C closed in
Status as of mid-October 2026, from the Q2 2026 report. Dates for future milestones are not shown because they can change.
Where construction stands
- Building A: finishing this month.
- Buildings B and C: framed and closed in. Framing started on Building B in April and on Building C at the end of June.
- Foundations: complete across the site.
What changed this quarter
- Permanent power is on. Seattle City Light installed the transformer.
- The condominium recorded in October, so each home can be sold and financed on its own.
- A bike room in Building C now has a repair station and outlets for e-bike charging.
- Site lighting, fences and gates are designed and will be installed before move-in.
What is next
Finishing Building A, then opening the model home.